A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?
During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?
Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?
A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?
A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
A project manager is assigned to a large, complex project that is very new to the organization. Because of huge expenditures, the project cannot be cancelled after it starts. Which of the following is most important for the project manager to do FIRST?
As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?
A project manager is discussing with team members sensitive project information that should not be disclosed outside of the office. Which of the following BEST describes this type of information?
Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each form. Which of the following compliance considerations BEST describes this scenario?
During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?
A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?
A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?
Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?
Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?
A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?
Which of the following methods frequently delivers new code in an automatic way for development projects?
When trying to calculate the expected monetary value for using a particular vendor, which of the following charts would be BEST to use?
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?
DRAG DROP -
During a gate review meeting, the deliverable was rejected by the customer.
Review the dashboard.
Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
Part 2: Select the proper document(s) to be updated.
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?