QuestionQ24

VerifiedProject Management Concepts

A project manager has determined that a project's critical path is 243 days. However, because the standard deviation is eight days, the project manager wants to give stakeholders an estimate with 95% confidence. Which of the following time frames should the project manager communicate to the stakeholders?

Explanation

A 95% confidence estimate is approximately two standard deviations on either side of the expected duration. Two standard deviations equal 16 days, so the range is 243 − 16 to 243 + 16 days, or 227–259 days.