During a brainstorming session, a team member raised concerns that solar flares might cause intermittent outages for individuals working on the project. Which of the following is the best tool for communicating this information to stakeholders?

Explanation

Solar flares are a potential future source of disruption, making them a risk. A risk report communicates project risk information to stakeholders, while a risk register is the detailed record used to document and manage risks.