QuestionQ12

VerifiedProject Management Concepts

Because of several changes, approval of the project scope baseline has been delayed. The project sponsor has limited the budget for this project. What should the project manager MOST likely do to move forward?

Explanation

Affected stakeholders need to be informed and engaged so that the changed scope, budget constraint, and required approvals can be aligned before work proceeds. Scope-baseline approval belongs to the appropriate authority, and changes require communication and coordination; a project manager should not independently reduce scope or alter the sponsor-imposed budget.