QuestionQ1

VerifiedProject Life Cycle Phases

A project manager will perform a release on the third Friday of the month. The project manager has informed users that the application will be unavailable for eight hours; therefore, users must save any information beforehand. Which of the following is the project manager most likely conducting?

Explanation

A maintenance window schedule defines a planned period when an application may be unavailable so releases, updates, or other maintenance can be performed. Advance notice allows users to prepare for the expected downtime.