QuestionQ2

Tools and Documentation

Which of the following would help a project manager clearly identify dependencies among project tasks by supporting critical-path calculation?

  • A Network diagram
  • B Project charter
  • C Project status report
  • D Gantt chart
Explanation

A network diagram maps project activities and their logical dependencies, providing the structure needed to identify the sequence of dependent tasks that determines the critical path.