QuestionQ3

VerifiedProject Management Concepts

Functional managers hesitate to provide a project manager with resources because they believe the project should contain a particular scope. The project manager reviews the project documentation and confirms that the items the functional managers want included are out of scope. What is the best course of action for the project manager to take?

Explanation

Work that is outside the approved scope must be evaluated through the formal change-control process. A resource-related disagreement that may prevent the project from obtaining required resources should be documented as an issue and escalated to the project sponsor for resolution.