QuestionQ8

Project Life Cycle Phases

A project manager and team are presently in the planning phase of a project. Which of the following should the team do during this phase?

  • A Identify and assess stakeholders.
  • B Hold daily status meetings.
  • C Remove access and plan the project sign-off.
  • D Review assumptions and constraints for input to the risk register.
Explanation

During project planning, the team identifies and analyzes risks. Assumptions and constraints can introduce uncertainty or limit project options, so reviewing them provides inputs for identifying and documenting risks in the risk register.