QuestionQ10

VerifiedTools and Documentation

Following an internal audit, a project manager implements a change that the CCB has approved.

Which change control process action should the project manager perform next?

Explanation

After an approved change is implemented, it must be validated to confirm that the implementation was completed successfully and conforms to the approved change.