QuestionQ5

VerifiedTools and Documentation

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite FIRST?

Explanation

Standard procurement sequencing starts with a Request for Information (RFI) to gather details on prospective vendors' capabilities and experience before soliciting formal proposals or quotes. Since the project team has no experience with the needed work, the project manager should expedite an RFI first to identify qualified vendors, then follow with an RFP or RFQ once viable candidates are known.