Free preview mode

Enjoy the free questions and consider upgrading to gain full access!

PRINCE2-FoundationFree trialFree trial

By prince2
Aug, 2025

Verified

25Q per page

Question 26

Which is a purpose of the Risk theme?

  • A: Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • B: Establish a cost-effective procedure to identify, assess and control uncertainty
  • C: Establish mechanisms to control any unacceptable deviations from plan
  • D: Establish mechanisms to manage risks at the corporate or programme level of an organization

Question 27

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

  • A: change budget
  • B: project budget
  • C: project's cost tolerance
  • D: project's risk tolerance

Question 28

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A: Risk category
  • B: Risk description
  • C: Risk response
  • D: Risk status

Question 29

Which describes a risk effect?

  • A: The uncertainty expressed as a negative or favourable occurrence
  • B: The issue which is affecting the project and has resulted in a risk
  • C: The impact(s) on the project objectives should the threat or opportunity occur
  • D: The change in the status of a risk in response to actions taken to control it

Question 30

Which describes risk probability?

  • A: Level of risks which the project can tolerate before escalating to the Project Board
  • B: Probable effect on the project delivering its objectives
  • C: Timeframe within which the risk may occur
  • D: A measure of the likelihood of the risk occurring

Question 31

Which is a purpose of a Risk Register?

  • A: Capture risks that may occur during the project
  • B: Record how risk management activities will be undertaken on the project
  • C: Record the risk tolerance for the project
  • D: Capture issues which are impacting on the delivery of the project objectives

Question 32

Which is the Issue Register NOT used for?

  • A: Capture external events that are impacting a stage
  • B: Record information about a deviation in stage tolerance
  • C: Capture any threats or opportunities that might have an impact on a stage
  • D: Record any problems identified when authorizing a Work Package

Question 33

Which role is responsible for ensuring the project is justified in terms of cost?

  • A: Project manager
  • B: Executive
  • C: Senior user
  • D: Senior supplier

Question 34

What is described as an organization's unique attitude towards risk taking

  • A: Risk appetite
  • B: Risk management
  • C: Risk evaluation
  • D: Risk tolerance

Question 35

Which is a purpose of the Risk Register?

  • A: Describe the risk management techniques and standards to be applied to the project
  • B: Act as a central record of information relating to the identified risks for the project
  • C: Act as a repository for informal issues
  • D: List the responsibilities for achieving an effective risk management procedure

Question 36

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

  • A: Controlling a Stage
  • B: Closing a Project
  • C: Directing a Project
  • D: Managing a Stage Boundary

Question 37

Which is a purpose of the Managing a Stage Boundary process?

  • A: Provide the Project Board with sufficient information for approving the next stage
  • B: Approve the next Stage Plan
  • C: Review and close any risks and issues identified during the previous stage
  • D: Control the link between the Project Manager and the Team Manager(s)

Question 38

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  • A: End Stage Report
  • B: Team Plan
  • C: Work Package
  • D: Project Plan

Question 39

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

  • A: Team Plan
  • B: Stage Plan
  • C: Benefits Review Plan
  • D: Project Plan

Question 40

Which activity takes place within the Managing a Stage Boundary process?

  • A: Produce Highlight Reports
  • B: Take corrective action within the limits of a stage's tolerance
  • C: Produce an Exception Plan
  • D: Authorize a Stage Plan for the next stage

Question 41

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

  • A: Checkpoint Report
  • B: Highlight Report
  • C: Issue Report
  • D: Product Status Account

Question 42

Which is a purpose of a Project Brief?

  • A: Enable the assembly of the project mandate
  • B: Describe the reporting requirements of the various layers of management involved with the project
  • C: Describe how changes to products will be controlled
  • D: Provide a solid basis for the initiation of the project

Question 43

Which is an objective of the Starting up a Project process?

  • A: Identify who will be responsible for creating the Project Plan
  • B: Agree how the project will be monitored and controlled after initiation
  • C: Authorize the Project Manager to proceed with the initiation stage
  • D: Agree how issues and changes will be identified, assessed and controlled

Question 44

Which is created during the Starting up a Project process?

  • A: Project mandate
  • B: Project management team role descriptions
  • C: Communication Management Strategy
  • D: Quality Register

Question 45

Which should be provided by corporate or programme management before the Starting up a Project process commences?

  • A: A Project Brief
  • B: Sufficient information to identify the prospective Executive
  • C: The Project Initiation Documentation
  • D: Authority to initiate a project

Question 46

How is the tailoring approach defined for a project?

  • A: The project board approves the approach
  • B: The project board documents the approach
  • C: Project assurance approves the approach
  • D: Project assurance documents the approach

Question 47

Which is a purpose of the change theme?

  • A: To prevent change to baselined products
  • B: To identify, assess and control any potential and approved changes to baselined products
  • C: To establish mechanisms to monitor and compare actual achievements against those planned
  • D: To assess and control uncertainty

Question 48

Which is the purpose of the Change theme?

  • A: To prevent change to baselined products
  • B: To identify, assess and control any potential and approved changes to baselined products
  • C: To establish mechanisms to monitor and compare actual achievements against those planned
  • D: To assess and control uncertainty

Question 49

Why is a project brief produced?

  • A: To act as a trigger for the 'starting up a project' process
  • B: To record the how the project will communicate with its stakeholders
  • C: To provide a full and firm foundation for the initiation of a project
  • D: To be used by the project board as a basis for reviewing the progress of a project

Question 50

Which is a key decision made during the 'directing a project' process?

  • A: Select and appoint the project executive
  • B: Approve the project manager role description
  • C: Confirm that the benefits management approach addresses all expected benefits
  • D: Approve the proposed project mandate
Page 2 of 14 • Questions 26-50 of 343

Free preview mode

Enjoy the free questions and consider upgrading to gain full access!