About the Exam

Professional-level HPE exam required for the HPE Aruba Networking Certified Professional - Data Center Architect credential, aimed at senior network engineers, consultants and solutions architects. Its 70 questions follow the design cycle: gathering and analyzing customer requirements, architecting the solution (product selection, segments, protocols, security), and documenting and presenting it. Passing demonstrates the ability to design multi-site data center networks.

Exam Topics

  • Determine customer's requirements19%
  • Analyze requirements25%
  • Architect the solution39%
  • Prepare and present the solution17%

How to Use This Practice Exam

  1. Browse — Read each question, select your answer, and reveal the explanation.
  2. Exam Mode — Simulate real exam conditions with a timed session and score report.
  3. Learn Mode — Spaced repetition schedules questions you struggle with for long-term retention.

Download the Full Exam PDF

Get every question and answer in a clean, printable PDF built for offline study. Purchase once, keep permanent access, and re-download the latest version anytime.

Last updated July 21, 2026 at 11:55 PM

Topic filter
Question status
Question sort
Questions per page

QuestionQ1

VerifiedAnalyze requirements

You are engaged by a customer with 1,115 employees to update the network after the previous network manager has left the company.

Which methods can validate the present network state when the available network documentation is out of date?

Choose two
Explanation

Physical inspection and cable tracing establish the actual device-to-device connections and cabling in use. Neighbor-discovery protocols such as CDP and LLDP automatically identify directly connected devices and their interfaces, providing observed relationship data from which a current topology can be documented. Cisco describes CDP and LLDP as device-discovery protocols that allow network management applications to automatically discover connected devices.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!

QuestionQ2

VerifiedDetermine customer's requirements

To prepare for a data center network implementation, you asked a customer for a list of VLANs to support. The customer’s list for several VMware ESXi hosts includes 4095.

What follow-up question should you ask?

Explanation

On a VMware ESXi standard-switch port group, VLAN ID 4095 enables Virtual Guest Tagging (VGT) rather than identifying an ordinary VLAN. The virtual machines connected to that port group apply the actual VLAN tags, so those tag values must be identified for the physical network configuration.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!

QuestionQ3

VerifiedDetermine customer's requirements

Which details should you seek to identify during the initial data-center network design meetings with the customer?

Choose two
Explanation

The deployment type—greenfield or brownfield—determines whether the design can be built without legacy constraints or must integrate with and migrate existing infrastructure. The project budget is an essential business constraint that determines which architecture, scale, resiliency, and implementation options are feasible.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!

QuestionQ4

VerifiedDetermine customer's requirements

Refer to the rack requirements in the scenario. What additional information would help you select between the CX 8325-48Y8C and CX 8360-48Y6C models?

Explanation

The 10-GbE-to-25-GbE port mix, including whether it may change, is decisive because the CX 8325-48Y8C uses interface groups for 10-GbE operation, while the CX 8360-48Y6C permits individually detected speeds on most SFP28 ports. Knowing the mix determines whether the CX 8325 port-group constraint is acceptable or the CX 8360’s greater per-port flexibility is required.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!

QuestionQ5

VerifiedAnalyze requirements

Waratah Hospital, located in Australia, plans to move many data-center services to a new facility. (The remaining legacy data center is outside the scope of this project.) Waratah Hospital has engaged an external consultant to help design the new data-center network.

Based on the data-center network-infrastructure requirements, the external consultant has produced a high-level design. The design document is summarized below.

Requirements and information:

  • Six racks in the data-center room (a single row).
  • Redundant top-of-rack leaf switches with back-to-front cooling in each rack, delivering 10/25 Gbps connectivity to servers, storage, and other devices.
  • Four 100 GbE uplinks per leaf switch.
  • The customer requested that all switch ports face the rear of the racks (the hot aisle).
  • OOB management for servers, storage, and the network must be provided through an external switch with back-to-front cooling. This switch must be included in the solution. One OOB switch provides connectivity for two racks.
  • Core equipment for the OOBM network is being reused.
  • Middle-of-row spine switches.
  • The data center must connect to the hospital building with links providing 400 Gbps.
  • Internet access is supplied through an existing firewall cluster with two firewalls, with one firewall in each data room. The second firewall operates in standby mode, and VRRP is used for firewall failover. The data-center network must connect to these firewalls with links totaling 100 Gbps.
  • The external link is a dark-fiber direct link based on single-mode fiber (OS2). The distance to the main hospital is 1.5 KM. The links will terminate on two core switches in the hospital.

The customer also requires:

  • 99.999% uptime for this life-critical environment.
  • Planned and unplanned downtime must be minimized.
  • Software upgrades are permitted only once per year with close to zero downtime.
  • All life-critical resources are accessed locally, and all resources exist within the hospital campus.
  • Waratah Hospital requires a highly secure data-center environment. Encrypted wire-speed connectivity between the data room and the hospital is mandatory because the link between the buildings crosses a public road.
  • Waratah Hospital has a mix of virtualized (vSphere) servers, Nutanix storage, bare-metal servers, backup servers, and other devices.

In the past, the hospital experienced a security breach that caused data loss, network downtime, and identity theft.

Given the scenario, what environmental information should be gathered to supplement the design?

Choose two
Explanation

Power requirements are needed to size and validate the facility’s electrical supply, redundant power paths, and power distribution for the proposed equipment. Heat-dissipation requirements are needed to size cooling and maintain acceptable intake temperatures and airflow. Cisco hardware documentation treats both maximum power provisioning and heat dissipation as installation-planning inputs; inadequate airflow or excess ambient temperature can cause thermal alarms or shutdowns.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!