QuestionQ15

VerifiedPrepare and present the solution

A long-time customer has just acquired a company and plans to bring the new data-center sites up to its standards. The customer has requested a bill of materials based only on the locations and port counts at the data-center sites.

Which valid assumptions should be documented in the proposal?

Choose two
Explanation

A data-center equipment proposal must state physical deployment assumptions when site surveys have not confirmed them. The existing racks must have sufficient space and suitability for the equipment, and the cooling design must support the equipment’s required airflow direction. Cisco installation guidance requires equipment to take in air from the cold aisle and exhaust it to the hot aisle, and identifies both front-to-back and back-to-front airflow configurations.