Log In / Sign UpScenario: Global Mobile 1 -
Global Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. Global Mobile actually has better coverage in nearly all markets than Air Light, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. Global Mobile has selected TOGAF 9 as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Corporate
Board has placed one additional major constraint on the program. In addition to achieving the business outcomes directly related to improving overall customer service within each business unit, the Corporate Board expects the Target Architecture to produce an additional saving of at least 30% over current operating costs through energy efficiency initiatives, virtualization of servers and workstations, and expanded telecommuting and desk-sharing. This Green initiative is intended to become a model for future investments at all company facilities worldwide.
You have been engaged as a consultant to advise the Chief Architect on the best ways to approach to the implementation planning activities for this significant business transformation.
Based on TOGAF 9, which of the following is the best answer? (Is this the right answers to choose?)
MightyGears produces components for the Car industry. Driven by the global financial downturn they are looking to reduce IT costs. They believe there is a cost saving opportunity within IT but this is not quantified in terms of potential savings nor is there an agreed target architecture. Final decisions on the solutions are not yet fully agreed. They have completed the first pass architecture and now are looking at the best opportunities and solutions to meet their financial goals.
You are the Chief Architect from a consulting organization brought into review the work to date by MightyGears and to make recommendations to the CIO and the board on the opportunities and solutions present.
Which of the following answers best describes how TOGAF recommends examining the opportunities and solutions before presenting to the board?
Choose one of the following answers
Scenario -
Your role is consultant to the Lead Architect within a multinational semiconductor and software design company. Its largest business is in processors, although it also designs system-on-a-chip infrastructure and manufactures memory chips. A characteristic feature of its processors is their low electric power consumption, which makes them particularly suitable for use in portable devices. As well as licensing its technology, the company has several manufacturing divisions.
The company has a mature enterprise architecture practice and uses TOGAF Standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
The company has defined a strategic architecture to improve its ability to meet customer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple Enterprise Resource Planning (ERP) applications that have been operating independently in the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new ERP product running as a single instance in the company's primary data center.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment. They have also completed the Implementation and Migration Plan v0.1, the draft Architecture Roadmap, and the Capability Assessment deliverables.
Because of the risks posed by the complexity of the current environment, it has been determined that a phased approach is needed to implement the target architectures. The overall implementation process is estimated to take several years.
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF Standard Version 9.2, which of the following is the best answer?
Scenario -
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops photovoltaic technologies for use in large-scale solar power farms.
The company has three manufacturing facilities, two in the United States, and one in Southern France. Each of these facilities supplies a different manufacturer that assembles and sells complete systems. The solar panels and photovoltaic arrays are custom engineered to meet each manufacturer's design specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a conventional solar panel overheats, it becomes inefficient and generates less energy. In response to this, the research arm of the company has pioneered the development of a new solar panel design that will produce up to
50% more energy than standard solar panels when operating at elevated temperatures. This will allow the production of significantly more useable energy per square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and systems used to design, manufacture and test the solar power technologies they produce. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new solar panel design into production, a pilot architecture project at a single location has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The
Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and high yields.
The Lead Enterprise Architect has asked you to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF, which of the following is the best answer?
You are serving as the Lead Architect for a chain of convenience stores, operating as a franchise, which has over 5000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours a day and 7 days a week and rely on point-of-sale technology to manage their inventory.
Stores place all orders on-line. The back-office systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible.
An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better accommodate the changing strategies within the company and also better respond to changes in economic and technical environments.
The CIO has stated that the following issues need to be addressed in the restructuring:
✑ The systems should be able to withstand any unforeseen disruptions which might affect day to day operations. This is highly critical for ensuring high levels of customer satisfaction and maintaining and growing revenue.
✑ Dependencies between the application components, the application platform, and technology infrastructure should be minimal and well defined. This will facilitate scalability and ease of enhancement of the service offerings.
✑ The company is adopting the ARTS Operational Data Model and Data Warehouse Model from the National Retail Federation. This will address past problems with data quality and inconsistent data.
✑ To remain competitive, new products and promotions must undergo market trials and if these are successful, deployed across the retail chain. Information systems must be able to manage changes and updates without undue delays.
[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference text in order to answer this question.]
You have been asked to identify the most relevant architecture principles for the current situation.
Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles listed in each answer is not significant.]
Scenario:
You have been assigned the role of Lead Enterprise Architect for a manufacturing firm that specializes in musical instruments. The firm has been established for over 100 years, operating in North America for most of that time. In the last ten years, the firm has expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion.
Each business unit has acquired other producers to expand its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program within the firm has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are pint sponsors of the EA program. The EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to the four target geographic markets. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work to address the goals of the reorganization has been approved. As the architecture team commences its work, the CIO has expressed concerns about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks.
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?
Scenario:
Your role is that of Lead Enterprise Architect within a vacation property management firm that has been growing through acquisition. The firm manages over 200 resort properties across North America. Many of the resort properties use the same internal IT systems that they used before they were acquired. Until recently, the only requirement that has been placed on each property is that they use a standard financial reporting system to report their financial results to the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified the need to change. He has defined a new strategic vision that will enhance the business by standardizing its operations across the network to provide consolidated financial, human resources, logistics, sales and marketing, and yield management. He has also stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient operations. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising into key markets to improve yields.
The firm has a mature enterprise architecture practice and uses TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire firm, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the firm has taken the decision to adopt a packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
You have been asked by the Chief Architect to justify the best approach for architecture development to realize the CEO's vision.
Based on TOGAF 9, which of the following is the best answer?
Scenario -
You have been appointed as a consultant to the Chief Enterprise Architect of a multinational pharmaceutical corporation. The corporation includes 30 subsidiary companies with operations in over 60 countries and products sold in over 125 countries. It has major research and development sites in over 45 locations worldwide.
The management team is deeply committed to ensuring that the corporation is a world leader in socially responsible pharmaceutical development with a business strategy that focuses on profitability through environmentally friendly operating processes as well as a commitment to disease eradication.
The operations of the corporation are subject to legal and regulatory requirements for each country where they operate. The production of prescription pharmaceutical products has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was conducting a clinical trial for a new regulated drug.
The Governing Board is concerned about the risks posed in this complex global environment. As a result the Chief Executive Officer (CEO) has appointed a Chief
Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program. He has requested to be informed about the status of projects that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed architectures to ensure that they are within the legal guidelines for each country. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance
Officer, legal staff, auditors and the research organization.
Based on TOGAF, which of the following is the best answer?
Scenario -
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to "leverage the synergies" that had been intended when the company was formed. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF 9 has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
In the Preliminary Phase you need to define suitable policies and ensure that the company has the appropriate capability to address the concerns of the Corporate
Board.
Based on TOGAF, which of the following is the best answer?
Scenario -
You are serving as the Lead Architect for an insurance company, which has been formed through the merger of three previously independent companies. The company now consists of three divisions with the same names and division headquarters as their predecessors.
The lack of integration between the three divisions has increasingly caused problems in the handling of customer and financial information. The inability to share information has resulted in lost opportunities to leverage the synergies that should have been possible as a result of the merger. At present, each division maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, and claims information, each division has different ways of defining these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a common web portal, contact center software suite, and document management system. Also the company has selected a single enterprise-wide customer relationship management (CRM) application to consolidate information from several applications that exist across the divisions. The application will be used by each of the divisions and accessed by third party partners through well defined interfaces.
The Corporate Board is concerned that the new application must be able to manage and safeguard confidential customer information in a secure manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services in cooperation with its partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the implementation team and the migration teams in each division. The CIO has also formed a cross-functional Architecture Board to oversee and govern the architecture. The company has an existing team of security architects.
TOGAF Standard Version 9.2 -
has been selected as the core framework for use for the Enterprise Architecture program. The CIO has endorsed this choice with the full support of top management.
As part of the process for establishing the Enterprise Architecture department, you are developing a set of architecture principles to guide the activities.
You need to recommend the best approach for this work.
Based on TOGAF Standard Version 9.2, which of the following is the best answer?
You are serving as the Lead Architect for a chain of convenience stores, which has over 2000 retail outlets throughout the Asia-Pacific region. The stores operate
24 hours a day and 7 days a week and use the latest cloud-based point-of-sale (POS) technology to manage their sales and inventory. Cloud-based POS systems store all user data, including sales and inventory in a remote server.
The cloud-based systems collect real-time data to support ordering and product selection decisions including the tailoring of product assortment based on sales history, customer demographics as well as the next day's weather forecast. In many cases, several stores are located in neighboring areas. This strategy makes distribution to each store cheaper, as well as making multiple deliveries per day possible. The stores also act as self-service delivery locations for a large online retailer which further increases the number of potential customers entering the stores.
An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to restructure the Enterprise Architecture so that it can better support the existing environment and accommodate future changes of strategy within the company.
The CIO has stated that the following issues also need to be addressed in the restructuring:
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops wind turbines for use in wind farms. The company has three manufacturing facilities, one in North America, one in Asia, and one in Europe. Each of these facilities supplies the power industry in its region.
The company recognizes that the long-term technical potential of wind energy can address the current global dependency on carbon fuels, in order to do so this will require wind turbines to be installed over the large areas and in areas of higher wind resources. In particular offshore wind farms can contribute substantially more energy than land stationed turbines.
The research arm of the company has pioneered the development of an offshore wind turbine design, with an improved turbine blade and power system, that will produce up to 20% more energy. This will allow the production of significantly more salable energy. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice supported by a cross-functional Architecture Board and uses the TOGAF standard. The Chief
Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new design into production, a pilot architecture project has defined an updated standard approach for controlling the automated test systems used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new automated test system controller for each location. The
Chief Engineer has expressed concern that a uniform process be employed at each location to ensure consistency and a low blade failure rate.
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
Scenario: Vittronics Ltd.
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market.
However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative
Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9.
The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
You are serving as the Lead Architect for the SPICE project team.
As required by TOGAF, the SPICE project team res completed a Business Transformation Readiness Assessment in Phase A (Architecture Vision). In that assessment, it was determined that there are risks associated with the adoption of the Immersive Collaborative Environment. Despite a clear expression of the vision and the business need for utilizing SPICE to accelerate the clinical trials, the researchers have been resisting the change because of concerns about safeguarding individually identifiable information about the subjects who were participating in the trials.
You have been asked to recommend how this situation be managed in the implementation planning phases.
Based on TOGAF 9, which of the following is the best answer?
Scenario:
You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self- directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management team is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The international operations of the company are subject to legal and regulatory requirements for each country where they operate. The production of genetically modified seeds has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Governing Board, legal staff, auditors and the research organization.
Based on TOGAF 9, which of the following is the best answer?
Scenario: Raxlon Inc.
Case Study Title (Case Study):
Raxlon Inc. is a Fortune 500 Company dealing in high value drugs and pharma products. Its annual turnover is over 120 billion $. It has more than 100,000 employees all over the globe in its R&D, Manufacturing and Marketing Units.
Raxlon's CEO, Dr Peter Fowles, is a pharmacology expert and has over 72 patents on various types of drugs mainly used for treating patients with genetic disorders. Raxlon is now moving into a suite of high end critical drug products used for Genetic Repair of congenital Diseases like Alzhmeir's disease and
Epilepsy. Rexlon has a well developed EA practice and in 2009 the EA practice has adopted TOGAF 9 as the primary Framework for Enterprise Architectural
Change Agent.
Dr Fowles' main concerns are:
Security of the critical data which they have gained over the years after painstaking research. Although Rexlon had an adequate security system Dr Fowles feels it may not be adequate to deal with the new order of things, especially with data which is highly confidential and if leaked would have major financial impact on the
Company.
Dr Fowles calls his CIO and explains his position to him and entrusts whim with the responsibly of evaluating the current security system, operation and governance and determine which are the gaps which need to be addressed during the fresh architectural work. Assume that a new Security Framework would be used in the ADM life cycle. To protect Rexlon's valuable IP.
The CIO apprises the Lead Architect of the sensitive nature of the work he has to complete within the next 2 months.
Identify which of the following processes would be most appropriate for the Lead Architect to adopt in this situation.
Scenario: MegaMart -
Case Study Title (Case Study):
MegaMart is a Retail Chain which has expanded throughout India and the Far East.
The CEO and CIO decide that there is a crying need to put an Enterprise Architecture in place to realize MegaMart's strategy to expand its revenue and diversify.
The CIO has evaluated and decided to go in for TOGAF9 and adapt it to his enterprise requirements.
The Preliminary and Vision Phase have been completed.
As such very few architectural artifacts exist and the target architecture as of now is not very clear. As the Lead Architect how would you guide your team of architects for the Business Architecture definition?
You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation. It is organized into two major business groupings:
✑ Upstream operations which include exploration for crude oil and natural gas and operating the infrastructure necessary to deliver oil and gas to the market
✑ Downstream operations which include the manufacturing, distribution and marketing activities for oil products and chemicals. Safety is a priority for the company, with the aim to ensure it causes zero harm to people and the environment. The company has to satisfy the regulatory requirements of each of the countries it operates in.
The downstream business generates a third of the company's profits worldwide and includes more than 30,000 petrol stations and various oil refineries. In some countries it also includes oil refining, a retail petrol station network, lubricans manufacture and marketing, industrial fuel and lubricans sales. The practice for the downstream business has been to operate locally, managed by local "operating companies".
The Governing Board is concerned about the risk posed by operating in this complex global environment with a large part of the downstrean business represented by local operating companies. As a result, the Chief Executive Officer (CEO) has appoimted a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues to the corporation. The CCO reports directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture program, and has mandated the use of the TOGAF standard as the framework. He has requested to be
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance
Officer, legal staff, auditors and the local operating companies.
Based on the TOGAF Standard, Version 9.2, which of the following is the best answer?
Your role is that of Lead Enterprise Architect for a chain of convenience stores. The chain includes over 15,000 retail outlets throughout the Asia-Pacific region.
Each store in the chain is an independently owned and operated franchise. The stores operate 24 hours a day and 7 days a week. Many of the stores have been wirh the franchise for more than 10 years and still use the original IT systems deployed at that time.
The CEO of the chain has stated his concerns about the inefficiencies of the current systems and identified the need to change. He has defined a new strategic vision that will enhance the business by providing its franchisees new services to help them complete with other retail outlets and online retailers. This strategy is part of the long-term commitment to enhance the brand image and increase revenue for the chain. He has also stated that he expects improved financial results by the end of the current fiscal year.
The changes will help provide the chain with improved products, and more efficient operations. The stores will also act as delivery and return locations for a large online retailer which will further increase the number of potential customers. The addition of a corporate-wide data warehouse will provide analytics that will enable the marketing group to improve its ability to target advertising and new products to specific regions.
The chain has a mature Enterprise Architecture practice based in its headquarters and uses the TOGAF standard as the method and guiding framework. The CIO is the sponsor of the activity.
The Chief Architect engaged the services of a leading consulting firm that specializes in business strategy. An initial study has been conducted to identify the strategic changes needed to implement the CEO's vision. This recently completed with approval of a strategic architecture encompassing the entire chin, including detailed requirements and recommendations.
Based on the recommendations from the initial study, the decision for the chain to adopt a packegd suite of integrated applications that is tailored to the needs of the franchise has been taken.
You have been asked by the Chief Architect to propose the best approach for architecture development to realize the CEO's vision.
Based on the TOGAF Standard, Version 9.2 which of the following is the best answer?
Scenario -
You are serving as the Lead Architect for the Enterprise Architecture team at a multinational company. The company has grown rapidly by acquisition and has inherited numerous supply chain processes and related IT systems. Several supply chain processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant processes and systems. The company will move to a "Just-in-time" supply chain management so as to keep inventory costs low.
The TOGAF standard is followed for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture
Development Method (ADM).
At present, there are no architectural assets in the Architecture Repository related to this initiative. All assets will need to be acquired, customized, or created. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing supply chain management processes or systems.
The architecture development project has completed Phase A and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:
Scenario: AGEX Inc.
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise
Architecture program.
The CIO has endorsed this choice with the full support of top management.
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that the Corporate Board's concern is addressed.
Based on TOGAF 9, which of the following is the best answer?
Dante Manufacturing is a big supplier in the automotive industry, head quarter in London with main plants in New York, Milan, Toronto and Tokio. Each one of these plants has been operating its own Manufacturing Requirements Planning (MRP II) system, production scheduling and custom applications for production automation. Dante's objective is to minimize waste production improving production operations. During an analysis of the process improvements was determined that a significant improvement on waste production could be achieved replacing the outdated MRPII system with a common Enterprise Resource Planning (ERP) located in London. Dante has well-developed governance and processes based on TOGAF 9. The Chief Engineer of Global Manufacturing operations is the business sponsor and issued a Request for Architectural Work. The architectural activity for the implementation of the new ERP platform is kicked off and the architectural vision is produced. Some concerns on the security, reliability, responsibility and time to manage change of driving the MRP II and production scheduling by a central system located in London are raised by the team of architects working on the project and by senior management of the various organizations. These last in particular, stressed the need to align the information management with the business.
As Lead Architect you have been asked to update the IT architectural principles to address the concerns raised by the project stakeholders and the senior management. According to TOGAF 9 (assuming the enterprise is using the example set of principles in TOGAF 9 Section 23.6), which of the following is the best answer?
Choose one of the following answers
Scenario: Marona Inc.
Marona Inc is a Fortune 500 Enterprise in the retail industry with retail store components manufacturing units and marketing outlets spanning the globe and having an annual turnover of 20 billion$ with more than 100, 000 employees world wide.
The CEO, CIO and the stakeholders of the ongoing EA projects are concerned about rising costs and as one measure want to do an investigation into the operational aspects of the realized Enterprise Architecture using TOGAF9.
The CIO approaches you as the Lead Enterprise Architect to carry out this exercise the stakeholder had voiced to him the following concerns:
They want to analyze the roles of the top management for each revenue earning service. Moreover, many of the HR related critical Search application component have become extremely slow. This needs to be diagnosed and rectified. Moreover there is no proper tracking of revenue from retail store component products over time. There has also been a lot of unauthorized or unwanted access to many of the critical information.
Hence the mode of access needs to be strengthened and made much more secure. Another additional concern is the new launches and the progress of each of the launches over time.
Determine which of the following set of viewpoints are most appropriate to analyze and view in order to address this concern of the stakeholders.
Scenario: St. Croix Consulting -
St. Croix Consulting started as an accounting and financial services company. It has expanded over the years and is now a leading North American IT and
Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management has become challenging.
The company does not want to risk its outstanding reputation or its international certifications and CMM ratings. Senior partners must become team players, working to support the broader needs of the company and its shareholders.
The Enterprise Architecture team has been working to create St. Croixs Enterprise Architecture framework to address these issues. The team has defined a preliminary framework and held workshops with key stakeholders to define a set of principles to govern the architecture work. They have completed an
Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Enterprise Architecture framework is based on TOGAF 9.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the Enterprise Architecture program.
You have been assigned to the role of Chief Enterprise Architect.
As the EA team prepares to formulate an Implementation plan, they have been asked by the CIO to assess the risks associated with the proposed architecture.
He has received concerns from senior management that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF 9, which of the following is the best answer?
Scenario:
You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board. The Chief Information Officer and the
Chief Operating Officer co-sponsor the Enterprise Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location.
The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?