Question 1

Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?

  • A: ‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
  • B: ‘Enable altering of planned date for task in WIP/Closed’.
  • C: ‘Rollup project start date from tasks’.
  • D: ‘Calculate ROI percentage based on a project's estimated cost and its net value’.

Question 2

Can an it_project_manager convert a task to a milestone?

  • A: No, this can only be done by a system admin.
  • B: Yes, by right-clicking on the task in the Planning Console.
  • C: No, the PPS admin role is also required.
  • D: Yes, if the task is assigned to the project manager.

Question 3

What is the formula for Forecasted Utilization?

  • A: Assigned Hours/Capacity
  • B: Confirmed Hours/Capacity
  • C: (Allocated Hours + Confirmed Hours)/Capacity
  • D: Allocated Hours/Capacity

Question 4

Resource plan costs are divided into: (Choose three.)

  • A: Planned Cost
  • B: Allocated Cost
  • C: Actual Cost
  • D: Expense Cost
  • E: Forecast Cost

Question 5

Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.

  • A: pm_toplevel_project
  • B: project_template_config
  • C: pm_home_page_config
  • D: pm_project

Question 6

As a demand manager, you can view an artifact from a demand. What artifacts are part of a demand?

  • A: Stories, Vulnerability Tasks, Enhancements.
  • B: Project, Defect, Requests.
  • C: Incidents, Problems, Change.
  • D: Decision, Risk, Requirements.

Question 7

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?

  • A: Front Load.
  • B: Back Load.
  • C: Any.
  • D: Even.

Question 8

If the ‘Move project for WIP projects’ property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states? (Choose two.)

  • A: Work in Progress
  • B: Closed
  • C: Pending
  • D: Open -

Question 9

Depending on the execution type selected for a particular project, one of these dashboards will also be available:

  • A: User Manager Dashboard
  • B: Timecard Dashboard
  • C: PMO Dashboard
  • D: Project Summary - Waterfall Dashboard

Question 10

The Project management application supports two types of external dependencies. What are they? (Choose two.)

  • A: Change Dependency.
  • B: Hard Dependency.
  • C: Task Dependency.
  • D: Soft Dependency.
  • E: Milestone Dependency.

Question 11

The combination of the user and the assigned portfolio must be unique when adding a user to which registry?

  • A: Stakeholder Registry.
  • B: Application Registry.
  • C: UX Page Registry.
  • D: Event Registry.

That’s the end of your free questions

You’ve reached the preview limit for CIS-SPM

Consider upgrading to gain full access!

Page 1 of 3 • Questions 1-25 of 52

Free preview mode

Enjoy the free questions and consider upgrading to gain full access!