Question 1
Whose interests are specifically represented by the senior supplier?
- Those ensuring the project is value for money.
- Those who will use the project's products.
- Those who will be developing the project's products.
- Those responsible for the project's technical integrity.
- A: 1 and 2
- B: 2 and 3
- C: 3 and 4
- D: 1 and 4
Question 2
Which BEST describes the senior user role when tailoring the organization theme?
- A: An 'agile sponsor'
- B: An 'executive sponsor'
- C: A 'coach'
- D: A 'super product owner'
Question 3
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A: Work in progress limit
- B: Information radiator
- C: Highlight report
- D: Glad! Sad! Mad!
Question 4
Which two statements about tailoring the business case in an agile environment are CORRECT?
- It should be unnecessary because products of the highest value will be delivered first.
- It should identify the minimum viable product and when it will be delivered.
- It should take into account that the scope may be reduced during the course of the project.
- It should show the features, the order in which they will be delivered and any dependencies.
- A: 1 and 2
- B: 2 and 3
- C: 3 and 4
- D: 1 and 4
Question 5
What should the business case state about the minimum viable product (MVP)?
- A: When the MVP will be defined
- B: That the MVP must go into operational use
- C: What the MVP is
- D: That the MVP is the same as project viability
Question 6
Which statement about the 'keep teams stable' target is CORRECT?
- A: It applies primarily to the long term, such as a project or a program
- B: It is the primary reason why the tolerance for cost is set to zero
- C: It prevents compromising the overall quality level of the product
- D: It results in the early delivery of a minimum viable product
Question 7
What needs to happen when new detailed requirements are added to a timebox?
- A: Requirements of a similar level of effort should be removed
- B: More people should be added to the delivery team
- C: The delivery milestones should be reviewed and re-planned
- D: Formal change control should be applied
Question 8
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- A: It gives confidence on the progress of the project
- B: It can result in the early delivery of a minimum viable product
- C: It allows misunderstandings to be dealt with appropriately
- D: It is achieved by managing the culture of the team carefully
Question 9
Which statement about velocity is CORRECT?
- A: It is based on the concept of rationalism
- B: It is shown by the ideal line on a bum-down chart
- C: It describes how much work is getting done
- D: It tracks the time and cost of a timebox
Question 10
Which is a purpose of the 'controlling stage' process?
- A: To execute and deliver the project product
- B: To establish whether the project is complete
- C: To report stage progress to the project board
- D: To draft the plan for the next stage's work
Question 11
Which is a key objective of running a workshop?
- A: To make daily progress visible to the delivery team and key stakeholders
- B: To encourage collaboration and create the defined outputs from the event
- C: To communicate decisions to the wider stakeholder community
- D: To make day-to-day decisions on behalf of the delivery team within a sprint
That’s the end of your free questions
You’ve reached the preview limit for PRINCE2 Agile FoundationConsider upgrading to gain full access!
Free preview mode
Enjoy the free questions and consider upgrading to gain full access!