QuestionQ6

VerifiedProcess

A company has selected a supplier to deliver software and assigned an internal project manager. The supplier says that the customer will not need to perform any technical development or testing. The project manager wants to validate this with all stakeholders.

What should the internal project manager do first?

Explanation

Stakeholder alignment is needed to confirm and document the project requirements, including each party’s responsibilities for development and testing. This establishes a shared, approved basis before preparing acceptance-test plans, changing supplier expectations, or communicating the project plan.