A customer is worried about the time needed to finish a project and asks the project team to reduce the number of iterations needed to complete the product.

Which approach should the project manager use?

Explanation

Prioritizing deliverables by business value ensures that the most important capabilities are completed first. Frequent releases make those capabilities available to the customer earlier, reducing time to realized value without arbitrarily shortening the iterative delivery process.