QuestionQ7

VerifiedProcess

A key stakeholder on the project team raises an additional requirement that could affect the overall schedule. A conversation with another stakeholder indicates that it may be only a small task.

What should the project manager do?

Explanation

A newly raised requirement must be clarified sufficiently to determine its scope, effort, dependencies, and schedule impact before it can be evaluated, planned, or processed through change control.