QuestionQ18

VerifiedProcess

A project sponsor maintains that the scope for a new product launch should cover two geographical locations. However, after the project scoping session was completed, the project charter was finalized and approved for only one location.

What should the project manager do?

Explanation

An additional geographical location is a change to the approved project scope. The project manager should assess its effects and submit a change request for approval before adding it to the project scope.