An agile project has a wide range of product features designed for different user profiles and uses. Defining common acceptance criteria that apply to every feature is difficult.

How can the project manager ensure the appropriate acceptance criteria are applied to the features?

Explanation

Feature-specific acceptance criteria should be established as part of the Definition of Ready so implementation begins with clear, applicable conditions of acceptance. The Definition of Done should include the associated tests that verify those conditions were met before the feature is considered complete.