QuestionQ17
VerifiedProcessA project manager conducted a meeting and developed the project schedule. A critical stakeholder who was not consulted during the schedule discussion complained that the published dates are unacceptable because of a prescheduled task for another assignment.
What should the project manager do first?
Community Discussion