QuestionQ12

VerifiedProcess

An organization is launching a project that will use new technology. Its complexity requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor requests options to reduce labor costs without adding risk to project delivery.

What should the project manager do first?

Explanation

Analyzing the key cost drivers establishes which labor costs are material and enables alternatives to be evaluated for cost savings, feasibility, and delivery risk before changing staffing or resource assignments.

Community Discussion

No comments yet. Be the first to start the discussion!