QuestionQ12
VerifiedProcessAn organization is launching a project that will use new technology. Its complexity requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor requests options to reduce labor costs without adding risk to project delivery.
What should the project manager do first?