QuestionQ13

VerifiedProcess

An organization is moving to agile delivery and has formed a new team. A project is performing poorly because team-velocity variation is very high and each sprint delivers less than was committed. A new project lead with strong technical expertise has been assigned to the project.

What should the project lead do?

Explanation

A Sprint Retrospective is used to inspect the team’s processes and identify improvements that increase effectiveness. Recommending that the team evaluate and potentially change its estimation method addresses the unreliable forecasts and recurring under-delivery while preserving team-based estimation and continuous improvement.