QuestionQ11

VerifiedProcess

After issuing an on-site invitation to seven people for a project's kick-off meeting, a key stakeholder declines because they will be at another location for the remainder of the month.

What should the project manager do?

Explanation

A key stakeholder should be able to participate in the project kick-off. Arranging virtual participation for that stakeholder maintains the planned on-site meeting for the other attendees while avoiding an unnecessary delay.