QuestionQ28

VerifiedManaging the Test Activities

You are the Test Manager for a new project developing a software system that must be certified to Level B of the DO-178B standard. The project will use a V-Model software development life cycle and will include four formal test levels: component, integration, system, and acceptance testing.

You must prepare the test-plan documentation for this project, ensuring adequate coordination across the four test levels to support auditability.

Which of the following best describes how the test plan should be organized?

Explanation

A master test plan establishes the overall test strategy and the relationships, dependencies, and coordination among all test levels. Separate detailed test plans for component, integration, system, and acceptance testing define the objectives, scope, techniques, resources, schedules, entry and exit criteria, and evidence for each level. This hierarchy preserves both end-to-end traceability and the detailed, auditable control required at each test level. FAA guidance for DO-178B identifies software verification planning as certification data that must be available for the software-planning review.

Learn more