QuestionQ29
VerifiedManaging the Test ActivitiesBased on historical data from five previous, similar projects, you calculated the following average numbers of defects detected during system testing:
- 200 defects for every 10,000 LOC (lines of code)
- 49 defects for each person-month of development-team effort
You want to use this information to estimate a new project.
The project manager estimates that this new project will contain 20,000 new LOC. Four developers work on the project for four months before system testing. During system testing, 797 defects are discovered. Assume that system testing for this new project uses the same amount of work as was spent on the past projects.
Based only on this information, which of the following statements is certainly true about this project?
Community Discussion