QuestionQ27

VerifiedManaging the Test Activities

You are the Test Manager for a new project that will include three formal testing levels: unit, integration, and system testing. The testing strategy you choose combines risk-based testing and reactive testing strategies.

Which answer gives the most consistent example of implementing this test strategy during execution of the system tests?

Explanation

Risk-based testing uses preplanned tests to address identified product risks, while reactive testing commonly uses exploratory testing that is designed and executed in response to knowledge gained during testing. Combining scripted, risk-focused system tests with exploratory sessions throughout the system-test phase implements both strategies.