QuestionQ26
VerifiedManaging the Test ActivitiesAssume you are the Test Manager for a small banking-application development project.
You have chosen a risk-based testing strategy, and five product risks (R1, R2, R3, R4, and R5) were identified during the quality risk analysis. The following table shows the risk level for these product risks (higher numbers indicate higher risk):

Fifty-five test cases have been designed and implemented to cover all five product risks. Their coverage is described in a traceability matrix.
This is the test-execution status table after the first week of test execution. About 56% of the planned test cases have been successfully executed. Assume that no additional product risks were identified during the first week of test execution.

Which answer would you expect to best describe the residual risks associated with the identified product risks at the end of the first week of test execution?