QuestionQ26

VerifiedManaging the Test Activities

Assume you are the Test Manager for a small banking-application development project.

You have chosen a risk-based testing strategy, and five product risks (R1, R2, R3, R4, and R5) were identified during the quality risk analysis. The following table shows the risk level for these product risks (higher numbers indicate higher risk):

Question Image

Fifty-five test cases have been designed and implemented to cover all five product risks. Their coverage is described in a traceability matrix.

This is the test-execution status table after the first week of test execution. About 56% of the planned test cases have been successfully executed. Assume that no additional product risks were identified during the first week of test execution.

Question Image

Which answer would you expect to best describe the residual risks associated with the identified product risks at the end of the first week of test execution?

Explanation

Residual risk is not reduced by the overall percentage of passed or executed test cases. It must be evaluated against the affected product risks and the unresolved evidence: failed or unrun tests and open defects. Without knowing the risk level associated with those open defects and outstanding test results, the table cannot indicate the residual risk level. Risk-based testing can report residual risk at any point in testing; it does not require every planned test to have been executed.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!