QuestionQ25

VerifiedManaging the Test Activities

Assume you are the Test Manager for a small insurance-application development project.

You have chosen a risk-based testing strategy: five product risks (R1, R2, R3, R4, R5) have been identified and their risk levels assessed. Ten test cases (T1, , T10) have been designed to cover all product risks.

The following table shows the risk level and the test cases associated with the identified product risks (a higher risk level indicates higher risk):

Question Image

You are not confident in the risk-level assessment and suspect that high-priority bugs could be found in low-risk areas. In addition, the test-execution period is very short. Your goal is to test all product risks in a risk-based manner while ensuring that each product risk receives at least some testing.

Which of the following answers describes the best test-execution schedule in this scenario?

Explanation

Executing one test case for each product risk first ensures every risk area receives testing despite the short execution period and uncertainty in the risk assessment. The remaining test cases are then run in descending assessed-risk order, concentrating additional effort on the highest-risk areas.