QuestionQ17
VerifiedManaging the Test ActivitiesYou are conducting a quality risk analysis for a CSCI (Computer Software Configuration Item) that implements a CBIT (Continuous Built-In Test) module in a safety-critical system.
During this quality risk analysis, you seek to identify the ways failures of the CBIT module may occur and, for each one, determine the potential causes, likely effects, and risk level (calculated as the product of three factors: severity, occurrence, and detection).
Which of the following risk analysis techniques are you using?