QuestionQ18

VerifiedManaging the Product

You are working on a project to build an authentication system for an e-commerce website. The system provides two features: registration and authentication.

Two separate development teams are developing these two features.

There is a high likelihood that delivery of the authentication feature to the test team will be three weeks late. To complete registration, the user must provide the following registration inputs: name, surname, birth date, fiscal code, and may choose a username and password.

A registered user may be a special user or a normal user. To be identified as a special user, the user must also provide, during the registration process, a voucher that may have been received from the IT department.

Access is granted only when a user is registered and the password is correct; in every other case, access is denied. If the registered user is a special user and the password is incorrect, a special warning is displayed on the system console.

You are currently conducting a quality risk analysis using FMEA.

Based only on the information provided, which of the following is NOT a product risk that could be identified during the quality risk analysis?

Explanation

A delayed delivery to the test team that could shorten the test period is a project risk because it affects the schedule and management of testing rather than a quality characteristic or behavior of the authentication system. Product risks include missing or incorrect functionality, such as granting access with an incorrect password or failing to show the required warning. The ISTQB CTFL syllabus classifies delays in work-product delivery as project risks and wrong or missing functionality as product risks.

Learn more