QuestionQ16

VerifiedManaging the Test Activities

Assume that you are managing the system-testing phase of a project.

The system-test execution period is scheduled for twenty weeks. All tests are manual, and you are following a risk-driven test approach.

During the latest staff meeting, the project manager gives you new deadlines that will not permit completion of all system tests. Which of the following would you expect to be the best response to this situation?

Explanation

Risk-driven testing allocates limited test time to the areas with the greatest product risk. When the schedule no longer permits all planned tests, execution should be reprioritized to cover the highest risks, while tracking those risks and any residual exposure.