QuestionQ63

VerifiedExecute

Which date type should an assignee update to change a task’s completion date?

Explanation

The Commit Date is the date by which the assigned user commits to completing the task. Only the assignee can update it, and changing it updates the task’s Projected Completion Date to match. The Planned Completion Date is the project owner’s planned schedule; the Actual Completion Date records when work was actually completed.