QuestionQ62
VerifiedExecuteTask 2 has a duration of 5 days, is linked to Task 1 as a predecessor, and is intended to start after Task 1 is complete. Because of a resource-availability conflict, Task 1 was rescheduled to begin 1 week later. After Task 1 was rescheduled, Task 2's planned start date did not dynamically move by the expected 5 days; instead, it stayed at the planned start date that existed before the Task 1 change.
What could have caused Task 2's planned start date to remain unchanged?