QuestionQ62

VerifiedExecute

Task 2 has a duration of 5 days, is linked to Task 1 as a predecessor, and is intended to start after Task 1 is complete. Because of a resource-availability conflict, Task 1 was rescheduled to begin 1 week later. After Task 1 was rescheduled, Task 2's planned start date did not dynamically move by the expected 5 days; instead, it stayed at the planned start date that existed before the Task 1 change.

What could have caused Task 2's planned start date to remain unchanged?

Explanation

In Adobe Workfront, manually updating a task’s Planned Start Date changes its Task Constraint to Must Start On. A Must Start On constraint schedules the task on that exact date and effectively ignores predecessor relationships, so a delay to its predecessor does not reschedule the task.