QuestionQ64

VerifiedIntake and planning

Taking into account any applied task constraints, a project manager needs to know the date a task is likely to finish based on its current progress and that of its predecessors.

Which date type should the project manager use?

Explanation

A projected date is the calculated expected finish date that accounts for current task progress, predecessor progress, dependencies, and applicable scheduling constraints.