QuestionQ48

VerifiedIntake and planning

A task was initially planned for a 10-day duration and 40 planned hours. The client requires it to be completed in 3 days.

Which task setting must be changed so that 4 users can finish it in fewer than 3 days?

Explanation

Effort-driven scheduling retains the task’s total 40 hours of work and redistributes that work when additional users are assigned, reducing the task duration. With four users, 40 hours can be completed in approximately 10 working hours, assuming equivalent availability and parallelizable work. Microsoft Project documents that effort-driven tasks keep total work constant and distribute remaining work to newly assigned resources.