QuestionQ48
VerifiedIntake and planningA task was initially planned for a 10-day duration and 40 planned hours. The client requires it to be completed in 3 days.
Which task setting must be changed so that 4 users can finish it in fewer than 3 days?
A task was initially planned for a 10-day duration and 40 planned hours. The client requires it to be completed in 3 days.
Which task setting must be changed so that 4 users can finish it in fewer than 3 days?