A task owner has recorded Time Off in Workfront for all of next week. She has a task that is planned to start and is due while she is away.

What action should the task owner take?

Explanation

The Commit Date is the completion date that the assigned task owner estimates they can realistically meet. Updating it communicates the impact of the planned absence to the project owner and updates the task’s projected completion date; task conditions do not revise that commitment.