QuestionQ47

VerifiedCloseout

A portfolio manager has accidentally granted Program Manager A excessive access to every project in their portfolio.

How can the portfolio manager correct this so that Program Manager A has Manage access only to their own program?

Explanation

A portfolio-level Manage permission grants broad control across the portfolio hierarchy. Granting Manage permission directly on the appropriate program while removing the portfolio-level Manage permission confines management rights to that program. Adobe Workfront documents that managing a program requires Manage permissions to the program, while portfolio management requires Manage permissions to the portfolio.