A team member has five days to finish a critical-path task, which requires only one hour of work. Today is the fourth day of that period, and the team member has not started it.

What effect does this have on the project’s progress status?

Explanation

Adobe Workfront calculates critical-path tasks as having no float, so a delay in such a task affects the project’s projected completion. When Condition Type is set to Progress Status, a project whose progress status is Behind or At Risk is automatically assigned the At Risk condition.