A marketing team decides that, going forward, the Project Sponsor must review its projects before they are closed.
What best practice ensures every project is appropriately reviewed and approved?
A project template can include a project approval process associated with the Complete status. Projects created from that template inherit the approval process, so the Project Sponsor must approve the project when it reaches completion. A global approval process is only available to be attached; it does not by itself ensure attachment to all projects.