QuestionQ28

Intake and planning

A project manager needs to see all assignees for every task in a project.

Which field should the manager reference to view all task assignees?

  • A Assigned To
  • B Assignments
  • C Assigned
Explanation

The Assignments reference contains the collection of assignment records for a task, allowing all resources assigned to that task to be viewed. Microsoft’s Project documentation shows that a task’s Assignments collection can be used to enumerate every resource assigned to it.