QuestionQ30Verified/Intake and planningCopy linkReport a problemAsk AstroTutorSave questionWhich project Condition is applied when the project's Progress Status is Behind or At Risk?ALateBAt RiskCIn TroubleShow AnswerAnswerExplanationAdobe Workfront automatically sets the project Condition to At Risk when the project Progress Status is Behind or At Risk. The In Trouble condition is used when the Progress Status is Late.Learn moreOverview of Project Condition and Condition TypeShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!