QuestionQ3

Complementary Practices

What could a Scrum Team visualize using Kanban?

Choose three
  • A The Product Backlog.
  • B The Sprint Backlog.
  • C The Definition of Done.
  • D The Sprint Retrospective.
Explanation

Kanban makes work, workflow states, and completion policies transparent. Product Backlog items can be visualized as they flow through the system, the Sprint Backlog can be shown to expose the current state of Sprint work, and the Definition of Done can be made visible as the shared criterion for completion. A Sprint Retrospective is an event for inspecting and improving the team’s process, not a work item or workflow policy.