QuestionQ2

Understanding and Applying the Scrum Framework

For a particular Sprint Backlog item that has already been started, which analytic is best for determining when it will be completed?

  • A Work Item Aging Chart.
  • B Throughput Run Chart.
  • C Control chart.
  • D Cumulative Flow diagram (CFD).
Explanation

A Work Item Aging Chart shows how long currently active work items have been in progress. Comparing an item’s age with the team’s normal completion pattern supports estimating when that started item is likely to be finished.