QuestionQ24

Understanding and Applying the Scrum Framework

A Scrum Team’s service level expectation (SLE) informs the different Scrum events. During which event does the SLE provide the greatest benefit for maintaining good flow?

  • A Sprint Retrospective.
  • B Sprint Review.
  • C Daily Scrum.
  • D Sprint Planning
Explanation

A service level expectation forecasts how long work items should take to flow from start to finish. Comparing the age of active work to the SLE during the Daily Scrum makes flow problems visible early and enables the Developers to adapt their plan, address blocked or queued work, and keep work moving.