QuestionQ23

Understanding and Applying the Scrum Framework

A Scrum Master is still required when Kanban practices are applied within the Scrum framework:

  • A It Depends.
  • B Always.
  • C Never.
Explanation

Scrum must be implemented as a complete framework, and it requires a Scrum Master. Kanban practices may complement Scrum but do not replace the Scrum Master’s accountability for establishing Scrum and enabling the Scrum Team’s effectiveness.

Learn more