QuestionQ41

VerifiedChange Sets

Universal Containers has several projects under development in parallel. One project is in the testing phase, and the testing team has identified a list of issues in items that will be deployed to production. Because the project deadline is short, the customer team proposes making the fixes in the test sandbox and then deploying them to Production.

What should the Architect recommend?

Explanation

Changes should be made in the development environment and promoted to the testing environment for validation before production deployment. This maintains a controlled release lifecycle, ensures the fixes are tested, and keeps the development environment aligned with the deployed release artifact.