QuestionQ1

VerifiedProcess

A project manager is assigned to a project that is part of a program. The project’s high-level requirements are known, but the priorities of certain requirements are uncertain because they depend on other pipeline projects within the program.

How should the project manager prepare for the project’s next steps?

Explanation

Program planning uses a high-level roadmap with milestones and preliminary estimates based on the information available, including applicable historical information. Known high-level requirements can therefore be prioritized and estimated at the milestone level while interproject dependencies and priorities are refined as program information becomes available.