QuestionQ73
DeliveryThe team underestimated a story’s complexity, which caused the work to be newly decomposed for delivery in the current sprint and required some items to be returned to the backlog.
What should the Scrum Master do next?
- A Ask the project manager to work with the product owner to help generate clearer stories in the future
- B Develop guidelines to prevent future occurrences
- C During the retrospective, discuss the issue and create an action plan to avoid it in the future
- D Allow the team to devise a corrective action without external intervention